Substation Scout

Pioneer Crossing LF

PJM queue ID Q59

Queue IDQ59
Project namePioneer Crossing LF
Status (as published)In Service
SubstationS. Reading-Birdsboro
Point of interconnectionS. Reading-Birdsboro 64kV
CountyBerks
StatePA
Voltage64 kV
Capacity6.4 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2008-05-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy6.4
Mw Capacity6.4
Mfo6.4

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.