PJM queue ID Q53

Chestnut Flats WF (Q53) is listed in the PJM interconnection queue as a 7.6 MW wind project in Blair County, PA. The filing names Summit-West Fall as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of May 20, 2011.

Queue IDQ53
Project nameChestnut Flats WF
Status (as published)In Service
SubstationSummit-West Fall
Point of interconnectionSummit-West Fall 115kV
CountyBlair
StatePA
Voltage115 kV
Capacity7.6 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2011-05-20
Source datasetserial

Same substation and county

Blair, PA: 15 requests in the PJM queue, 2 active totaling 19.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy38
MW capacity7.6
MFO38

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first