Substation Scout

Camp Grove Wind Farm

PJM queue ID L05_CE22

Camp Grove Wind Farm (L05_CE22) is listed in the PJM interconnection queue as a 30 MW wind project in Stark County, IL. The filing names Camp Grove as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 14, 2007.

Queue IDL05_CE22
Project nameCamp Grove Wind Farm
Status (as published)In Service
SubstationCamp Grove
Point of interconnectionCamp Grove
CountyStark
StateIL
VoltageNot reported
Capacity30 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2007-12-14
Source datasetserial

Same substation and county

Stark, IL: 9 requests in the PJM queue, 1 active totaling 30 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy150
MW capacity30
MFO150

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first