PJM queue ID I10

Bethesda (Sub 6) (I10) is listed in the PJM interconnection queue as a 2 MW gas project in Montgomery County, MD. PJM lists its status as “In Service”, with a target commercial operation date of October 1, 2004.

Queue IDI10
Project nameBethesda (Sub 6)
Status (as published)In Service
SubstationBethesda (Sub 6)
Point of interconnectionBethesda (Sub 6)
CountyMontgomery
StateMD
VoltageNot reported
Capacity2 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2004-10-01
Source datasetserial

Same substation and county

Montgomery, MD: 31 requests in the PJM queue, 15 active totaling 1,683.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy2
MFO2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.