Sparrow Point
PJM queue ID E05
Sparrow Point (E05) is listed in the PJM interconnection queue as a 2.5 MW gas project in Baltimore County, MD. The filing names Bethlehem Steel as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 1, 2001.
| Queue ID | E05 |
|---|---|
| Project name | Sparrow Point |
| Status (as published) | In Service |
| Substation | Bethlehem Steel |
| Point of interconnection | Bethlehem Steel 33kV |
| County | Baltimore County |
| State | MD |
| Voltage | 33 kV |
| Capacity | 2.5 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2001-01-01 |
| Source dataset | serial |
Same substation and county
Baltimore County, MD: 34 requests in the PJM queue, 5 active totaling 311 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 2.5 |
| MW capacity | 2.5 |
| MFO | 152.5 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.