Substation Scout

Waymart WF

PJM queue ID D05

Waymart WF (D05) is listed in the PJM interconnection queue as a 70 MW wind project in Wayne County, PA. The filing names East Carbondale as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 1, 2003.

Queue IDD05
Project nameWaymart WF
Status (as published)In Service
SubstationEast Carbondale
Point of interconnectionEast Carbondale 69kV
CountyWayne
StatePA
Voltage69 kV
Capacity70 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2003-12-01
Source datasetserial

Same substation and county

East Carbondale substation: 2 requests in the PJM queue, 2 active totaling 83 MW.

Queue IDProjectMWResourceStatus
K21Waymart13WindIn Service

Wayne, PA: 30 requests in the PJM queue, 4 active totaling 1,393.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy70
MFO70

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first