Shipley 34.5 kV
PJM queue ID C01-2244
Shipley 34.5 kV (C01-2244) is listed in the PJM interconnection queue as a 5 MW battery project in Anne Arundel County, MD. The filing names Shipley as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 1, 2030.
| Queue ID | C01-2244 |
|---|---|
| Project name | Shipley 34.5 kV |
| Status (as published) | Active |
| Substation | Shipley |
| Point of interconnection | Shipley 34.5 kV |
| County | Anne Arundel |
| State | MD |
| Voltage | 34.5 kV |
| Capacity | 5 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-06-01 |
| Source dataset | cycle |
Same substation and county
Anne Arundel, MD: 29 requests in the PJM queue, 11 active totaling 1,322.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Glen Burnie BERIC BESS LLC |
|---|---|
| Transmission owner | BGE |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 5.0 |
| MW capacity | 5.0 |
| MFO | 5.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/25/2026 |