Substation Scout

Unity - Rawlings 500 kV

PJM queue ID C01-2197

Queue IDC01-2197
Project nameUnity - Rawlings 500 kV
Status (as published)Active
SubstationUnity - Rawlings
Point of interconnectionUnity - Rawlings 500 kV
CountyBrunswick
StateVA
Voltage500 kV
Capacity200 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2030-06-01
Source datasetcycle

Additional filed fields

DeveloperHoneybee Energy Storage, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy200.0
Mw Capacity200.0
Mfo200.0
Submitted Date4/27/2026
Last Updated6/12/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.