New Post - Tributary 230 kV
PJM queue ID C01-2164
New Post - Tributary 230 kV (C01-2164) is listed in the PJM interconnection queue as a 400 MW battery project in Spotsylvania County, VA. The filing names New Post - Tributary as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 30, 2031.
| Queue ID | C01-2164 |
|---|---|
| Project name | New Post - Tributary 230 kV |
| Status (as published) | Active |
| Substation | New Post - Tributary |
| Point of interconnection | New Post - Tributary 230 kV |
| County | Spotsylvania |
| State | VA |
| Voltage | 230 kV |
| Capacity | 400 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2031-06-30 |
| Source dataset | cycle |
Same substation and county
Spotsylvania, VA: 17 requests in the PJM queue, 5 active totaling 1,337 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | AE Renewable Development, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 400.0 |
| MW capacity | 400.0 |
| MFO | 400.0 |
| Submitted date | 4/27/2026 |
| Last updated | 7/17/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.