TSS 903 Tovey 345 kV
PJM queue ID C01-2155
TSS 903 Tovey 345 kV (C01-2155) is listed in the PJM interconnection queue as a 18 MW battery project in Christian County, IL. The filing names TSS 903 Tovey as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of October 15, 2030.
| Queue ID | C01-2155 |
|---|---|
| Project name | TSS 903 Tovey 345 kV |
| Status (as published) | Active |
| Substation | TSS 903 Tovey |
| Point of interconnection | TSS 903 Tovey 345 kV |
| County | Christian |
| State | IL |
| Voltage | 345 kV |
| Capacity | 18 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-10-15 |
| Source dataset | cycle |
Same substation and county
TSS 903 Tovey substation: 2 requests in the PJM queue, 2 active totaling 518 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-2154 | TSS 903 Tovey 345 kV | 500 | Battery | Active |
Christian, IL: 18 requests in the PJM queue, 8 active totaling 1,125.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Black Diamond Solar Power, LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 0.0 |
| MW capacity | 18.0 |
| MFO | 30.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/25/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.