Substation Scout

Pickens - Monterville 138 kV

PJM queue ID C01-2095

Pickens - Monterville 138 kV (C01-2095) is listed in the PJM interconnection queue as a 182.7 MW wind project in Randolph County, WV. The filing names Pickens - Monterville as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2031.

Queue IDC01-2095
Project namePickens - Monterville 138 kV
Status (as published)Active
SubstationPickens - Monterville
Point of interconnectionPickens - Monterville 138 kV
CountyRandolph
StateWV
Voltage138 kV
Capacity182.7 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2031-12-31
Source datasetcycle

Same substation and county

Randolph, WV: 8 requests in the PJM queue, 3 active totaling 346.8 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperACE DevCo NC, LLC
Transmission ownerAPS
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy277.64
MW capacity182.712
MFO277.64
Submitted date4/27/2026
Last updated10/23/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.