Substation Scout

05GUARDN 138 kV

PJM queue ID C01-1989

05GUARDN 138 kV (C01-1989) is listed in the PJM interconnection queue as a 27.5 MW solar project in Noble County, IN. The filing names 05GUARDN as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of October 31, 2030.

Queue IDC01-1989
Project name05GUARDN 138 kV
Status (as published)Active
Substation05GUARDN
Point of interconnection05GUARDN 138 kV
CountyNoble
StateIN
Voltage138 kV
Capacity27.5 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2030-10-31
Source datasetcycle

Same substation and county

Noble, IN: 7 requests in the PJM queue, 1 active totaling 27.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperOriden LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy110.0
MW capacity27.5
MFO110.0
Submitted date4/27/2026
Last updated6/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.