Richland - Lockwood 138 kV

PJM queue ID C01-1983

Queue IDC01-1983
Project nameRichland - Lockwood 138 kV
Status (as published)Active
SubstationRichland - Lockwood
Point of interconnectionRichland - Lockwood 138 kV
CountyDefiance
StateOH
Voltage138 kV
Capacity58.5 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2030-06-01
Source datasetcycle

Additional filed fields

DeveloperDNPB1, LLC
Transmission OwnerATSI
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy60.0
Mw Capacity58.48
Mfo60.0
Submitted Date4/17/2026
Last Updated5/18/2026