Guernsey - Vassell 765 kV

PJM queue ID C01-1964

Guernsey - Vassell 765 kV (C01-1964) is listed in the PJM interconnection queue as a 931.1 MW gas project in Muskingum County, OH. The filing names Guernsey - Vassell as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 31, 2031.

Queue IDC01-1964
Project nameGuernsey - Vassell 765 kV
Status (as published)Active
SubstationGuernsey - Vassell
Point of interconnectionGuernsey - Vassell 765 kV
CountyMuskingum
StateOH
Voltage765 kV
Capacity931.1 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2031-05-31
Source datasetcycle

Same substation and county

Guernsey - Vassell substation: 2 requests in the PJM queue, 2 active totaling 1,862.2 MW.

Queue IDProjectMWResourceStatus
C01-1965Guernsey - Vassell 765 kV931.1GasActive

Muskingum, OH: 17 requests in the PJM queue, 6 active totaling 3,494.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperCortex Sycamore, LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy976.1
MW capacity931.1
MFO976.1
Submitted date4/26/2026
Last updated6/24/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.