Substation Scout

Muskingum, OH interconnection queue

7 active projects totalling 4,264.7 MW in the PJM queue, plus 10 with terminal status (shown greyed).

7active projects
4,264.7active MW
17total filed
Queue IDProjectkVMWResourceStatus
C01-1886 Ohio Central 345 kV 345 1,000 Battery Active
C01-1964 Guernsey - Vassell 765 kV 765 931.1 Gas Active
C01-1965 Guernsey - Vassell 765 kV 765 931.1 Gas Active
C01-1954 Muskingum River - Ohio Central 345 kV 345 770 Gas Active
S101 Dresden 138 580 Gas In Service
P02 Ohio Central 138kV 138 550 Gas Withdrawn
AH1-754 Not reported n/r 500 Battery Withdrawn
AC1-024 Frazeysburg 138kV 138 57 Solar Withdrawn
AD1-015 Muskingum Solar 138 57 Solar Withdrawn
AC1-100 Dresden 138 43.4 Gas In Service
AD2-151 Hillcrest 345kV 345 42 Solar Withdrawn
AH1-661 Cannelville 12.47 kV 12.5 9.1 Other Active
Y1-018 Conesville #5 n/r 5 Coal Deactivated
Y1-019 Conesville #6 n/r 5 Coal Deactivated
Z2-037 Clean River Power MR-7 (Philo) n/r 4 Hydro Withdrawn
AC2-054 South Rultonham 69kV 69 3.8 Solar Withdrawn
W3-063 Zanesville Energy n/r 0 Gas Deactivated

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.