South Butler - Varner 345 kV & South Butler - Dunton Lake 345 kV #1 & South Butler - Dunton Lake 345 kV #2
PJM queue ID C01-1952
| Queue ID | C01-1952 |
|---|---|
| Project name | South Butler - Varner 345 kV & South Butler - Dunton Lake 345 kV #1 & South Butler - Dunton Lake 345 kV #2 |
| Status (as published) | Active |
| Substation | South Butler - Varner & South Butler - Dunton Lake #1 & South Butler - Dunton Lake #2 |
| Point of interconnection | South Butler - Varner 345 kV & South Butler - Dunton Lake 345 kV #1 & South Butler - Dunton Lake 345 kV #2 |
| County | DeKalb |
| State | IN |
| Voltage | 345 kV |
| Capacity | 931.1 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2031-05-31 |
| Source dataset | cycle |
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Cortex Sycamore, LLC |
|---|---|
| Transmission Owner | AEP |
| Project Type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| Mw Energy | 976.1 |
| Mw Capacity | 931.1 |
| Mfo | 976.1 |
| Submitted Date | 4/24/2026 |
| Last Updated | 6/25/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.