Dennis 138 kV
PJM queue ID C01-1934
Dennis 138 kV (C01-1934) is listed in the PJM interconnection queue as a 180 MW battery project in Cape May County, NJ. The filing names Dennis as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2030.
| Queue ID | C01-1934 |
|---|---|
| Project name | Dennis 138 kV |
| Status (as published) | Active |
| Substation | Dennis |
| Point of interconnection | Dennis 138 kV |
| County | Cape May |
| State | NJ |
| Voltage | 138 kV |
| Capacity | 180 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-12-31 |
| Source dataset | cycle |
Same substation and county
Cape May, NJ: 36 requests in the PJM queue, 5 active totaling 289 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Great Cedar Storage LLC |
|---|---|
| Transmission owner | AEC |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 180.0 |
| MW capacity | 180.0 |
| MFO | 180.0 |
| Submitted date | 4/27/2026 |
| Last updated | 5/28/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.