Stonewall 138 kV

PJM queue ID C01-1910

Stonewall 138 kV (C01-1910) is listed in the PJM interconnection queue as a 150 MW battery project in Frederick County, MD. The filing names Stonewall as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 1, 2029.

Queue IDC01-1910
Project nameStonewall 138 kV
Status (as published)Active
SubstationStonewall
Point of interconnectionStonewall 138 kV
CountyFrederick
StateMD
Voltage138 kV
Capacity150 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-03-01
Source datasetcycle

Same substation and county

Stonewall substation: 2 requests in the PJM queue, 2 active totaling 300 MW.

Queue IDProjectMWResourceStatus
AG2-288Stonewall 138 kV150BatteryActive

Frederick, MD: 34 requests in the PJM queue, 8 active totaling 923.1 MW.

A substation with the same name is named in PJM transmission planning materials: Stonewall (APS, 4 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperVA-202 LLC
Transmission ownerAPS
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy150.0
MW capacity150.0
MFO150.0
Submitted date4/24/2026
Last updated8/31/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first