Statler Hill 115 kV

PJM queue ID C01-1807

Queue IDC01-1807
Project nameStatler Hill 115 kV
Status (as published)Active
SubstationStatler Hill
Point of interconnectionStatler Hill 115 kV
CountySomerset
StatePA
Voltage115 kV
Capacity12.9 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2028-06-01
Source datasetcycle

Additional filed fields

DeveloperForward WindPower LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy0.0
Mw Capacity12.85
Mfo29.4
Submitted Date4/27/2026
Last Updated6/23/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.