Substation Scout

AEP Sorenson - Dumont 345 kV

PJM queue ID C01-1707

Queue IDC01-1707
Project nameAEP Sorenson - Dumont 345 kV
Status (as published)Active
SubstationAEP Sorenson - Dumont
Point of interconnectionAEP Sorenson - Dumont 345 kV
CountySt. Joseph
StateIN
Voltage345 kV
Capacity187.5 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2030-12-01
Source datasetcycle

Additional filed fields

DeveloperRWE Clean Energy Land, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy250.0
Mw Capacity187.5
Mfo250.0
Submitted Date4/24/2026
Last Updated6/23/2026