New Baltimore 115 kV
PJM queue ID C01-1702
New Baltimore 115 kV (C01-1702) is listed in the PJM interconnection queue as a 13 MW wind project in Somerset County, PA. The filing names New Baltimore as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2027.
| Queue ID | C01-1702 |
|---|---|
| Project name | New Baltimore 115 kV |
| Status (as published) | Active |
| Substation | New Baltimore |
| Point of interconnection | New Baltimore 115 kV |
| County | Somerset |
| State | PA |
| Voltage | 115 kV |
| Capacity | 13 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | cycle |
Same substation and county
Somerset, PA: 107 requests in the PJM queue, 25 active totaling 286.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Stony Creek Wind Farm, LLC |
|---|---|
| Transmission owner | PENELEC |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 0.0 |
| MW capacity | 13.0 |
| MFO | 52.5 |
| Submitted date | 4/25/2026 |
| Last updated | 6/16/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.