W4-005 POI 345 kV
PJM queue ID C01-1700
W4-005 POI 345 kV (C01-1700) is listed in the PJM interconnection queue as a 110.8 MW wind project in DeWitt County, IL. The filing names W4-005 POI as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2027.
| Queue ID | C01-1700 |
|---|---|
| Project name | W4-005 POI 345 kV |
| Status (as published) | Active |
| Substation | W4-005 POI |
| Point of interconnection | W4-005 POI 345 kV |
| County | DeWitt |
| State | IL |
| Voltage | 345 kV |
| Capacity | 110.8 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | cycle |
Same substation and county
DeWitt, IL: 4 requests in the PJM queue, 3 active totaling 146 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Radfords Run Wind Farm, LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 0.0 |
| MW capacity | 110.8 |
| MFO | 306.0 |
| Submitted date | 4/24/2026 |
| Last updated | 6/23/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.