DeWitt, IL interconnection queue

3 active projects totalling 146 MW in the PJM queue, plus 1 with terminal status (shown greyed).

3active projects
146active MW
4total filed
Queue IDProjectkVMWResourceStatus
C01-1700 W4-005 POI 345 kV 345 110.8 Wind Active
AB2-070 Alta Farms II n/r 26 Wind In Service
U4-037 Brokaw-Lanesville 345kV 345 26 Wind Withdrawn
AF2-305 Alta Farms II 345 9.2 Wind In Service

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.