Gun Road 345 kV
PJM queue ID C01-1699
Gun Road 345 kV (C01-1699) is listed in the PJM interconnection queue as a 30.5 MW wind project in Champaign County, OH. The filing names Gun Road as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2027.
| Queue ID | C01-1699 |
|---|---|
| Project name | Gun Road 345 kV |
| Status (as published) | Active |
| Substation | Gun Road |
| Point of interconnection | Gun Road 345 kV |
| County | Champaign |
| State | OH |
| Voltage | 345 kV |
| Capacity | 30.5 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | cycle |
Same substation and county
Champaign, OH: 32 requests in the PJM queue, 5 active totaling 316.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Scioto Ridge Solar, LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 0.0 |
| MW capacity | 30.5 |
| MFO | 249.795 |
| Submitted date | 4/25/2026 |
| Last updated | 6/9/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.