Wylie Ridge - Tidd 345 kV (C01-1630) is listed in the PJM interconnection queue as a 750 MW gas project in Washington County, PA. The filing names Wylie Ridge - Tidd as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 1, 2031.

Queue IDC01-1630
Project nameWylie Ridge - Tidd 345 kV
Status (as published)Active
SubstationWylie Ridge - Tidd
Point of interconnectionWylie Ridge - Tidd 345 kV
CountyWashington
StatePA
Voltage345 kV
Capacity750 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2031-06-01
Source datasetcycle

Same substation and county

Washington, PA: 27 requests in the PJM queue, 8 active totaling 2,424.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperSeven Creek Energy, LLC
Transmission ownerAPS
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy750.0
MW capacity750.0
MFO750.0
Submitted date4/27/2026
Last updated6/17/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.