Substation Scout

TSS 905 Essex 345 kV

PJM queue ID C01-1567

TSS 905 Essex 345 kV (C01-1567) is listed in the PJM interconnection queue as a 150 MW wind project in Kankakee County, IL. The filing names TSS 905 Essex as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2028.

Queue IDC01-1567
Project nameTSS 905 Essex 345 kV
Status (as published)Active
SubstationTSS 905 Essex
Point of interconnectionTSS 905 Essex 345 kV
CountyKankakee
StateIL
Voltage345 kV
Capacity150 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Same substation and county

TSS 905 Essex substation: 2 requests in the PJM queue, 1 active totaling 150 MW.

Queue IDProjectMWResourceStatus
C01-1551TSS 905 Essex 345 kV480BatteryWithdrawn

Kankakee, IL: 42 requests in the PJM queue, 15 active totaling 1,494.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperIllinois Generation LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy0.0
MW capacity150.0
MFO850.0
Submitted date4/27/2026
Last updated6/17/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.