Davis Creek - Burnham 345 kV
PJM queue ID C01-1546
Davis Creek - Burnham 345 kV (C01-1546) is listed in the PJM interconnection queue as a 250 MW battery project in Will County, IL. The filing names Davis Creek - Burnham as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 1, 2031.
| Queue ID | C01-1546 |
|---|---|
| Project name | Davis Creek - Burnham 345 kV |
| Status (as published) | Active |
| Substation | Davis Creek - Burnham |
| Point of interconnection | Davis Creek - Burnham 345 kV |
| County | Will |
| State | IL |
| Voltage | 345 kV |
| Capacity | 250 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2031-05-01 |
| Source dataset | cycle |
Same substation and county
Will, IL: 66 requests in the PJM queue, 22 active totaling 3,615.4 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Ultraviolet Energy LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 250.0 |
| MW capacity | 250.0 |
| MFO | 250.0 |
| Submitted date | 4/27/2026 |
| Last updated | 9/1/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.