Aquasco 230 kV
PJM queue ID C01-1541
Aquasco 230 kV (C01-1541) is listed in the PJM interconnection queue as a 200 MW battery project in Prince George's County, MD. The filing names Aquasco as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of January 2, 2030.
| Queue ID | C01-1541 |
|---|---|
| Project name | Aquasco 230 kV |
| Status (as published) | Active |
| Substation | Aquasco |
| Point of interconnection | Aquasco 230 kV |
| County | Prince George's |
| State | MD |
| Voltage | 230 kV |
| Capacity | 200 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-01-02 |
| Source dataset | cycle |
Same substation and county
Aquasco substation: 2 requests in the PJM queue, 1 active totaling 200 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| X4-026 | Aquasco 230kV | 650 | Gas | Withdrawn |
Prince George's, MD: 57 requests in the PJM queue, 14 active totaling 3,551.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Beacon Power Project LLC |
|---|---|
| Transmission owner | PEPCO |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 200.0 |
| MW capacity | 200.0 |
| MFO | 200.0 |
| Submitted date | 4/27/2026 |
| Last updated | 9/1/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.