McLean 345 kV - Brokaw 345 kV 345 kV
PJM queue ID C01-1540
McLean 345 kV - Brokaw 345 kV 345 kV (C01-1540) is listed in the PJM interconnection queue as a solar request filed at 0 MW (a net change or energy-only filing) in McLean County, IL. The filing names McLean - Brokaw as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 1, 2032.
| Queue ID | C01-1540 |
|---|---|
| Project name | McLean 345 kV - Brokaw 345 kV 345 kV |
| Status (as published) | Active |
| Substation | McLean - Brokaw |
| Point of interconnection | McLean 345 kV - Brokaw 345 kV 345 kV |
| County | McLean |
| State | IL |
| Voltage | 345 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2032-06-01 |
| Source dataset | cycle |
Same substation and county
McLean - Brokaw substation: 3 requests in the PJM queue, 2 active totaling 0 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-1740 | McLean 345 kV - Brokaw 345 kV 345 kV | 0 | Solar | Active |
| C01-1741 | McLean 345 kV - Brokaw 345 kV 345 kV | 0 | Solar | Withdrawn |
McLean, IL: 41 requests in the PJM queue, 15 active totaling 1,021.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Wild Indigo Solar, LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 207.0 |
| MW capacity | 0.0 |
| MFO | 207.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/10/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.