Davis Besse 345 kV
PJM queue ID C01-1506
Davis Besse 345 kV (C01-1506) is listed in the PJM interconnection queue as a 80 MW nuclear project in Ottawa County, OH. The filing names Davis Besse as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2034.
| Queue ID | C01-1506 |
|---|---|
| Project name | Davis Besse 345 kV |
| Status (as published) | Active |
| Substation | Davis Besse |
| Point of interconnection | Davis Besse 345 kV |
| County | Ottawa |
| State | OH |
| Voltage | 345 kV |
| Capacity | 80 MW |
| Resource (as published) | Nuclear |
| Resource category | Nuclear (normalized for filtering) |
| Target commercial operation | 2034-12-01 |
| Source dataset | cycle |
Same substation and county
Ottawa, OH: 2 requests in the PJM queue, 1 active totaling 80 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Vistra Nuclear Operations Company |
|---|---|
| Transmission owner | ATSI |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 80.0 |
| MW capacity | 80.0 |
| MFO | 996.0 |
| Submitted date | 4/3/2026 |
| Last updated | 5/29/2026 |