Carson - Suffolk 500 kV (AE1-173 switching station)
PJM queue ID C01-1496
Carson - Suffolk 500 kV (AE1-173 switching station) (C01-1496) is listed in the PJM interconnection queue as a 240 MW battery project in Sussex County, VA. The filing names Carson - Suffolk (AE1-173 switching station) as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2030.
| Queue ID | C01-1496 |
|---|---|
| Project name | Carson - Suffolk 500 kV (AE1-173 switching station) |
| Status (as published) | Active |
| Substation | Carson - Suffolk (AE1-173 switching station) |
| Point of interconnection | Carson - Suffolk 500 kV (AE1-173 switching station) |
| County | Sussex |
| State | VA |
| Voltage | 500 kV |
| Capacity | 240 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-12-01 |
| Source dataset | cycle |
Same substation and county
Sussex, VA: 39 requests in the PJM queue, 14 active totaling 1,580.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Clenera DevCo, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 400.0 |
| MW capacity | 240.0 |
| MFO | 400.0 |
| Submitted date | 4/25/2026 |
| Last updated | 6/10/2026 |