Orchard - Cumberland 230 kV
PJM queue ID C01-1443
Orchard - Cumberland 230 kV (C01-1443) is listed in the PJM interconnection queue as a 350 MW battery project in Cumberland County, NJ. The filing names Orchard - Cumberland as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2030.
| Queue ID | C01-1443 |
|---|---|
| Project name | Orchard - Cumberland 230 kV |
| Status (as published) | Active |
| Substation | Orchard - Cumberland |
| Point of interconnection | Orchard - Cumberland 230 kV |
| County | Cumberland |
| State | NJ |
| Voltage | 230 kV |
| Capacity | 350 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-12-31 |
| Source dataset | cycle |
Same substation and county
Orchard - Cumberland substation: 2 requests in the PJM queue, 2 active totaling 500 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-1444 | Orchard - Cumberland 230 kV | 150 | Battery | Active |
Cumberland, NJ: 94 requests in the PJM queue, 15 active totaling 1,148.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Atlantic City Electric Company |
|---|---|
| Transmission owner | AEC |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 350.0 |
| MW capacity | 350.0 |
| MFO | 350.0 |
| Submitted date | 4/23/2026 |
| Last updated | 6/12/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.