Chinquapin - Everetts 230 kV
PJM queue ID C01-1371
Chinquapin - Everetts 230 kV (C01-1371) is listed in the PJM interconnection queue as a 60 MW solar project in Martin County, NC. The filing names Chinquapin - Everetts as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 31, 2029.
| Queue ID | C01-1371 |
|---|---|
| Project name | Chinquapin - Everetts 230 kV |
| Status (as published) | Active |
| Substation | Chinquapin - Everetts |
| Point of interconnection | Chinquapin - Everetts 230 kV |
| County | Martin |
| State | NC |
| Voltage | 230 kV |
| Capacity | 60 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2029-05-31 |
| Source dataset | cycle |
Same substation and county
Martin, NC: 9 requests in the PJM queue, 3 active totaling 120.5 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Rawls Solar LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 100.0 |
| MW capacity | 60.0 |
| MFO | 100.0 |
| Submitted date | 4/23/2026 |
| Last updated | 6/9/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.