Plano - Lasco Station 345 kV (C01-1336) is listed in the PJM interconnection queue as a 300 MW battery project in Kendall County, IL. The filing names Plano - Lasco Station as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2030.

Queue IDC01-1336
Project namePlano - Lasco Station 345 kV
Status (as published)Active
SubstationPlano - Lasco Station
Point of interconnectionPlano - Lasco Station 345 kV
CountyKendall
StateIL
Voltage345 kV
Capacity300 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Same substation and county

Plano - Lasco Station substation: 2 requests in the PJM queue, 1 active totaling 300 MW.

Queue IDProjectMWResourceStatus
C01-1708Plano - Lasco Station 345 kV125BatteryWithdrawn

Kendall, IL: 17 requests in the PJM queue, 3 active totaling 467.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperFox Valley Energy Facility, LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy300.0
MW capacity300.0
MFO300.0
Submitted date4/27/2026
Last updated6/4/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first