Broadford - Baker 765 kV
PJM queue ID C01-1326
Broadford - Baker 765 kV (C01-1326) is listed in the PJM interconnection queue as a 1,045 MW gas project in Wayne County, WV. The filing names Broadford - Baker as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of September 30, 2031.
| Queue ID | C01-1326 |
|---|---|
| Project name | Broadford - Baker 765 kV |
| Status (as published) | Active |
| Substation | Broadford - Baker |
| Point of interconnection | Broadford - Baker 765 kV |
| County | Wayne |
| State | WV |
| Voltage | 765 kV |
| Capacity | 1,045 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2031-09-30 |
| Source dataset | cycle |
Same substation and county
Wayne, WV: 3 requests in the PJM queue, 3 active totaling 1,069 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Appalachian Power Company |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 1045.0 |
| MW capacity | 1045.0 |
| MFO | 1045.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/26/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.