Ridgely 138 kV

PJM queue ID C01-1308

Ridgely 138 kV (C01-1308) is listed in the PJM interconnection queue as a 428.6 MW gas project in Licking County, OH. The filing names Ridgely as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 1, 2031.

Queue IDC01-1308
Project nameRidgely 138 kV
Status (as published)Active
SubstationRidgely
Point of interconnectionRidgely 138 kV
CountyLicking
StateOH
Voltage138 kV
Capacity428.6 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2031-06-01
Source datasetcycle

Same substation and county

Licking, OH: 23 requests in the PJM queue, 8 active totaling 1,039.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperSeminary Ridge Energy Center, LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy458.078
MW capacity428.588
MFO458.078
Submitted date4/27/2026
Last updated6/12/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first