Davis Besse - Beaver 345 kV
PJM queue ID C01-1258
Davis Besse - Beaver 345 kV (C01-1258) is listed in the PJM interconnection queue as a 103.1 MW wind project in Erie County, OH. The filing names Davis Besse - Beaver as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of April 9, 2026.
| Queue ID | C01-1258 |
|---|---|
| Project name | Davis Besse - Beaver 345 kV |
| Status (as published) | Active |
| Substation | Davis Besse - Beaver |
| Point of interconnection | Davis Besse - Beaver 345 kV |
| County | Erie |
| State | OH |
| Voltage | 345 kV |
| Capacity | 103.1 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2026-04-09 |
| Source dataset | cycle |
Same substation and county
Erie, OH: 12 requests in the PJM queue, 5 active totaling 262.8 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Firelands Wind, LLC |
|---|---|
| Transmission owner | ATSI |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 0.0 |
| MW capacity | 103.1 |
| MFO | 261.8 |
| Submitted date | 4/27/2026 |
| Last updated | 10/8/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.