Substation Scout

Kanawha - Sundial #2 138 kV

PJM queue ID C01-1251

Kanawha - Sundial #2 138 kV (C01-1251) is listed in the PJM interconnection queue as a 150 MW solar project in Boone County, WV. The filing names Kanawha - Sundial #2 as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of September 30, 2030.

Queue IDC01-1251
Project nameKanawha - Sundial #2 138 kV
Status (as published)Active
SubstationKanawha - Sundial #2
Point of interconnectionKanawha - Sundial #2 138 kV
CountyBoone
StateWV
Voltage138 kV
Capacity150 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2030-09-30
Source datasetcycle

Same substation and county

Boone, WV: 2 requests in the PJM queue, 2 active totaling 200 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperStony Pass Energy Center, LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy250.0
MW capacity150.0
MFO250.0
Submitted date4/27/2026
Last updated6/1/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first