Substation Scout

Boone, WV interconnection queue

2 active projects totaling 200 MW in the PJM queue.

2active projects
200active MW
2total filed
Queue IDProjectkVMWResourceStatus
C01-1251 Kanawha - Sundial #2 138 kV 138 150 Solar Active
C01-1669 Stink Run - Sundial 138 kV 138 50 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.