Substation Scout

Clinton 138 kV

PJM queue ID C01-1233

Clinton 138 kV (C01-1233) is listed in the PJM interconnection queue as a 180 MW battery project in Allegheny County, PA. The filing names Clinton as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 1, 2030.

Queue IDC01-1233
Project nameClinton 138 kV
Status (as published)Active
SubstationClinton
Point of interconnectionClinton 138 kV
CountyAllegheny
StatePA
Voltage138 kV
Capacity180 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2030-03-01
Source datasetcycle

Same substation and county

Clinton substation: 5 requests in the PJM queue, 3 active totaling 949.4 MW.

Queue IDProjectMWResourceStatus
X2-012Patriot Generating Station765GasIn Service
AC2-168Gaucho Solar4.4SolarIn Service
G49Clinton 69kV10GasWithdrawn
X4-043Allerton Road Solar Farm3SolarWithdrawn

Allegheny, PA: 64 requests in the PJM queue, 11 active totaling 1,589.8 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperPA-202 LLC
Transmission ownerDL
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy180.0
MW capacity180.0
MFO180.0
Submitted date4/15/2026
Last updated6/5/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.