Spurlock - Meldahl Dam 345 kV (C01-1227) is listed in the PJM interconnection queue as a 758 MW gas project in Mason County, KY. The filing names Spurlock - Meldahl Dam as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2031.

Queue IDC01-1227
Project nameSpurlock - Meldahl Dam 345 kV
Status (as published)Active
SubstationSpurlock - Meldahl Dam
Point of interconnectionSpurlock - Meldahl Dam 345 kV
CountyMason
StateKY
Voltage345 kV
Capacity758 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2031-12-31
Source datasetcycle

Same substation and county

Mason, KY: 8 requests in the PJM queue, 3 active totaling 908 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperEast Kentucky Power Cooperative, Inc.
Transmission ownerEKPC
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy780.0
MW capacity758.0
MFO780.0
Submitted date4/27/2026
Last updated6/9/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first