Fayette 345 kV (C01-1180) is listed in the PJM interconnection queue as a 500 MW gas project in Fayette County, OH. The filing names Fayette as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of September 1, 2028.

Queue IDC01-1180
Project nameFayette 345 kV
Status (as published)Active
SubstationFayette
Point of interconnectionFayette 345 kV
CountyFayette
StateOH
Voltage345 kV
Capacity500 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2028-09-01
Source datasetcycle

Same substation and county

Fayette, OH: 16 requests in the PJM queue, 3 active totaling 1,956.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperBluegrass Power Generation LLC
Transmission ownerDAYTON
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy500.0
MW capacity500.0
MFO500.0
Submitted date4/27/2026
Last updated10/19/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.