Substation Scout

Chenoweth 345 kV

PJM queue ID C01-1073

Chenoweth 345 kV (C01-1073) is listed in the PJM interconnection queue as a 87.4 MW solar project in Greene County, OH. The filing names Chenoweth as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of April 24, 2028.

Queue IDC01-1073
Project nameChenoweth 345 kV
Status (as published)Active
SubstationChenoweth
Point of interconnectionChenoweth 345 kV
CountyGreene
StateOH
Voltage345 kV
Capacity87.4 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-04-24
Source datasetcycle

Same substation and county

Greene, OH: 8 requests in the PJM queue, 1 active totaling 87.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperFox Squirrel Solar LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy0.0
MW capacity87.4
MFO577.0
Submitted date4/26/2026
Last updated6/17/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first