Gritty Run 69 kV
PJM queue ID C01-1068
Gritty Run 69 kV (C01-1068) is listed in the PJM interconnection queue as a 12.1 MW project in Pickaway County, OH. The filing names Gritty Run as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2027.
| Queue ID | C01-1068 |
|---|---|
| Project name | Gritty Run 69 kV |
| Status (as published) | Active |
| Substation | Gritty Run |
| Point of interconnection | Gritty Run 69 kV |
| County | Pickaway |
| State | OH |
| Voltage | 69 kV |
| Capacity | 12.1 MW |
| Resource (as published) | Other |
| Resource category | Other (normalized for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | cycle |
Same substation and county
Pickaway, OH: 35 requests in the PJM queue, 9 active totaling 196.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Tallgrass Columbus Community Power, LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 13.394 |
| MW capacity | 12.055 |
| MFO | 13.394 |
| Submitted date | 4/17/2026 |
| Last updated | 11/9/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.