Brambleton-Goose Creek 500kV
PJM queue ID AH1-727
Brambleton-Goose Creek 500kV (AH1-727) is listed in the PJM interconnection queue as a 425 MW battery project in Loudoun County, VA. The filing names Brambleton-Goose Creek as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 11, 2029.
| Queue ID | AH1-727 |
|---|---|
| Project name | Brambleton-Goose Creek 500kV |
| Status (as published) | Active |
| Substation | Brambleton-Goose Creek |
| Point of interconnection | Brambleton-Goose Creek 500kV |
| County | Loudoun |
| State | VA |
| Voltage | 500 kV |
| Capacity | 425 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-06-11 |
| Source dataset | cycle |
Same substation and county
Loudoun, VA: 22 requests in the PJM queue, 10 active totaling 1,922.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Cardinal Energy Storage East, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 425.0 |
| MW capacity | 425.0 |
| MFO | 425.0 |
| Submitted date | 4/10/2025 |
| Last updated | 8/22/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.