Bremo - Cartersville 230 kV
PJM queue ID AG2-583
Bremo - Cartersville 230 kV (AG2-583) is listed in the PJM interconnection queue as a 69 MW solar project in Cumberland County, VA. The filing names Bremo - Cartersville as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2028.
| Queue ID | AG2-583 |
|---|---|
| Project name | Bremo - Cartersville 230 kV |
| Status (as published) | Active |
| Substation | Bremo - Cartersville |
| Point of interconnection | Bremo - Cartersville 230 kV |
| County | Cumberland |
| State | VA |
| Voltage | 230 kV |
| Capacity | 69 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-12-01 |
| Source dataset | cycle |
Same substation and county
Cumberland, VA: 16 requests in the PJM queue, 5 active totaling 3,412 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Boston Hill Solar, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 115.0 |
| MW capacity | 69.0 |
| MFO | 115.0 |
| Submitted date | 3/31/2021 |
| Last updated | 8/11/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.