Substation Scout

Silver Lake 345 kV

PJM queue ID AG2-544

Silver Lake 345 kV (AG2-544) is listed in the PJM interconnection queue as a 80 MW battery project in McHenry County, IL. The filing names Silver Lake as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 20, 2029.

Queue IDAG2-544
Project nameSilver Lake 345 kV
Status (as published)Active
SubstationSilver Lake
Point of interconnectionSilver Lake 345 kV
CountyMcHenry
StateIL
Voltage345 kV
Capacity80 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-12-20
Source datasetcycle

Same substation and county

Silver Lake substation: 7 requests in the PJM queue, 2 active totaling 240 MW.

Queue IDProjectMWResourceStatus
AG2-545Silver Lake 345 kV160BatteryActive
Z2-041Silver Lake435GasWithdrawn
X2-019Silver Lake 345kV180GasWithdrawn
AG1-110Silver Lake 69 kV20BatteryWithdrawn
AE1-062Silver Lake 69 kV10BatteryWithdrawn
AF1-160Silver Lake 69 kV10BatteryWithdrawn

McHenry, IL: 35 requests in the PJM queue, 12 active totaling 1,510 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperMonarch Grid, LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleTC2
StagePhase 3
MW energy200.0
MW capacity80.0
MFO200.0
Submitted date3/31/2021
Last updated9/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first