Silver Lake 345 kV (AG2-544) is listed in the PJM interconnection queue as a 80 MW battery project in McHenry County, IL. The filing names Silver Lake as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 20, 2029.
| Queue ID | AG2-544 |
|---|---|
| Project name | Silver Lake 345 kV |
| Status (as published) | Active |
| Substation | Silver Lake |
| Point of interconnection | Silver Lake 345 kV |
| County | McHenry |
| State | IL |
| Voltage | 345 kV |
| Capacity | 80 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-12-20 |
| Source dataset | cycle |
Same substation and county
Silver Lake substation: 7 requests in the PJM queue, 2 active totaling 240 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG2-545 | Silver Lake 345 kV | 160 | Battery | Active |
| Z2-041 | Silver Lake | 435 | Gas | Withdrawn |
| X2-019 | Silver Lake 345kV | 180 | Gas | Withdrawn |
| AG1-110 | Silver Lake 69 kV | 20 | Battery | Withdrawn |
| AE1-062 | Silver Lake 69 kV | 10 | Battery | Withdrawn |
| AF1-160 | Silver Lake 69 kV | 10 | Battery | Withdrawn |
McHenry, IL: 35 requests in the PJM queue, 12 active totaling 1,510 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Monarch Grid, LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 200.0 |
| MW capacity | 80.0 |
| MFO | 200.0 |
| Submitted date | 3/31/2021 |
| Last updated | 9/11/2026 |