Substation Scout

Penns Tap-Richfield Tie 69 kV II

PJM queue ID AG2-479

Penns Tap-Richfield Tie 69 kV II (AG2-479) is listed in the PJM interconnection queue as a 4.1 MW solar project in Snyder County, PA. The filing names Penns Tap-Richfield Tie II as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 31, 2027.

Queue IDAG2-479
Project namePenns Tap-Richfield Tie 69 kV II
Status (as published)Active
SubstationPenns Tap-Richfield Tie II
Point of interconnectionPenns Tap-Richfield Tie 69 kV II
CountySnyder
StatePA
Voltage69 kV
Capacity4.1 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-03-31
Source datasetcycle

Same substation and county

Snyder, PA: 26 requests in the PJM queue, 10 active totaling 1,152.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperCottontail Solar 6, LLC
Transmission ownerPPL
Project typeGeneration Interconnection
CycleTC2
StagePhase 3
MW energy0.0
MW capacity4.1
MFO20.0
Submitted date3/31/2021
Last updated8/21/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.