Summersville - Magnolia 69 kV (AG2-424) is listed in the PJM interconnection queue as a 35 MW hybrid project in Larue County, KY. The filing names Summersville - Magnolia as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2027.
| Queue ID | AG2-424 |
|---|---|
| Project name | Summersville - Magnolia 69 kV |
| Status (as published) | Active |
| Substation | Summersville - Magnolia |
| Point of interconnection | Summersville - Magnolia 69 kV |
| County | Larue |
| State | KY |
| Voltage | 69 kV |
| Capacity | 35 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | cycle |
Same substation and county
Larue, KY: 2 requests in the PJM queue, 1 active totaling 35 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Magnolia Solar and Grazing Farm LLC |
|---|---|
| Transmission owner | EKPC |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 63.25 |
| MW capacity | 34.95 |
| MFO | 63.25 |
| Submitted date | 3/30/2021 |
| Last updated | 9/25/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.