Substation Scout

Crooksville 69 kV

PJM queue ID AG2-073

Queue IDAG2-073
Project nameCrooksville 69 kV
Status (as published)Active
SubstationCrooksville
Point of interconnectionCrooksville 69 kV
CountyMadison
StateKY
Voltage69 kV
Capacity50.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-09-01
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperSR Madison, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC2
StagePhase 3
Mw Energy53.0
Mw Capacity50.88
Mfo53.0
Submitted Date1/11/2021
Last Updated8/18/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.